Compliance is no guarantee of a low-energy building

Like
Liked

Date:

Head-and-shoulders shot of David Pierce of IES
David Pierce is Consultancy Manager, Building Energy Performance at IES.

With England’s Future Homes and Buildings Standards approaching, design teams need to test how buildings will operate before construction begins. Used alongside compliance assessment, dynamic simulation modelling (DSM) can reveal performance risks within a compliant design, helping engineers make informed decisions and reduce the risk of costly underperformance. By David Pierce of IES.

For a building owner, a gap between expected and actual energy use can mean higher running costs and missed carbon targets. Those consequences often emerge after key decisions about the fabric and building services have been made, leaving fewer opportunities to put things right.

England’s Future Homes and Buildings Standards sharpen the need to address that risk. The regulations take effect from 24 March 2027, with later commencement for certain higher-risk building provisions and transitional arrangements. The Future Buildings Standard is expected to drive improvements in fabric performance, building services efficiency and low-carbon heating. As compliance requirements become more demanding, understanding performance in use will be essential to turn those improvements into energy savings.

Regulatory compliance alone cannot establish whether a building will meet its operational energy and carbon targets. Preparing for the new standards should therefore include testing how each design will respond to realistic use, while there is still time to improve it.

fractals
The convergence of physical and virtual environments is opening new possibilities for understanding and managing the built environment. (Image credit: IES).

Compliance calculations have limits
Regulatory calculations use standard assumptions about occupancy, operating hours and energy demand. Those assumptions allow designs to be assessed consistently. They cannot capture every way a building will be used.

An office that stays open for two extra hours each evening has different demands from one that closes at five. A school opening its facilities to the community will consume energy beyond the teaching day. These are foreseeable variations that deserve attention during design.

The scope of the calculation also needs attention. In non-domestic buildings, catering equipment and server rooms can make substantial demands on energy, yet sit outside parts of a regulatory assessment. Owners pay for the whole building’s consumption. They need estimates that account for it.

The government’s Building for 2050 report, published in 2022, illustrates the performance gap. At the Marmalade Lane development in Cambridge, median annual space-heating energy use in the monitored houses and flats was around three times the developer’s SAP estimate. SAP, the Standard Assessment Procedure, uses standardised assumptions rather than predicting each household’s consumption.

The study covered a period that included pandemic restrictions, when occupancy differed from normal patterns. It also identified construction and system-performance issues. The findings show why a gap between a calculation and a meter reading needs investigation before anyone attributes it to occupants.

3D model of central Dublin around Trinity College, with a panel charting a retail building's simulated monthly energy use and carbon emissions
A Dublin town model displays estimates of energy consumption and emissions. (Image credit: IES).

The gap can begin before anyone moves in
At Marmalade Lane, tested air permeability was more than twice the value used in the developer’s SAP calculation. Researchers also found less roof insulation than specified in the houses. Such differences undermine the design on which predicted performance rests.

Project teams should therefore examine the energy implications of changes during delivery. If equipment changes during procurement, engineers should check how the replacement will operate within the wider system. Changes to insulation details should be checked for their effect on heat loss before work proceeds.

Commissioning deserves the same scrutiny. Efficient equipment can disappoint if controls are poorly configured or systems work against one another. Clear operating guidance is also essential: occupants and facilities managers need to understand how to run the building as intended, including the conditions on which its energy estimate depends.

Use simulation to improve the design
A useful operational assessment starts with the building’s likely use and makes uncertainties explicit. CIBSE’s TM54 guidance provides a framework for this, including operating hours, equipment demand and scenario testing. It supports several modelling approaches, with the choice shaped by the building and the questions being asked.

Whichever approach is chosen, the value of the exercise depends on its inputs. DSM can sit alongside a compliance assessment, with modelling variables tailored to the building to produce a realistic operational estimate. Where possible, designers should involve future operators in setting those variables and explain where uncertainty remains.

Using IESVE, engineers can simulate how a building responds over time as weather and solar gains interact with occupancy, equipment loads and building services. Hour-by-hour analysis can reveal when demand rises and how different systems respond, helping teams identify changes in operating conditions that could undermine performance.

That analysis should influence design decisions. Engineers can compare glazing and shading options to understand their combined effects on winter heating and summer cooling. They can also test how ventilation strategies or control schedules perform under different occupancy patterns, then use the findings to refine the design before equipment is specified and installed.

Longer opening hours or higher equipment loads can then be tested against that design. If a modest change causes a sharp rise in energy demand, the team can investigate the cause and assess alternatives. The client gains a clearer view of the likely range of consumption and the conditions needed to achieve the intended performance.

That evidence gives the client a basis for choosing between design options. A lower initial cost may come with higher energy demand over the building’s life. Making that trade-off explicit allows the team to assess running costs alongside construction costs, with the assumptions about energy prices and carbon emissions clearly stated.

3D model of central Dublin around Trinity College, with a panel charting a retail building's simulated monthly energy use and carbon emissions
Solar analysis of a data centre design. (Image credit: IES).

Carry the evidence through to occupation
The selected design then has to survive procurement and construction. Modelling cannot compensate for poor workmanship or commissioning. If significant design changes occur during construction, the energy model should be updated to reflect them. At handover, operators should understand the intended control settings and have a clear basis for comparing measured energy use with expectations.

That comparison must account for weather and actual use, with responsibility agreed for investigating differences. Post-occupancy evidence can reveal faults or assumptions that need revisiting, and help teams improve future projects.

Building owners preparing for the new standards should ask how operational targets have shaped the design, and which assumptions could put those targets at risk. Those questions belong in the brief from the outset. Waiting for the first energy bills leaves owners to deal with problems that could have been identified when the design was still open to change.